Cellulose Acetate Silk Company Ltd v Widnes Foundry (1925) Ltd

This document is only available to subscribers.

[1933] AC 20; HL Construction contract – measure of damages – delay – penalty sum per week agreed – liquidated damages – inadequacy of damages – whether limited to liquidated damages rather than actual loss suffered In this case, a contract for the construction of an acetone recovery plant provided...

This page is only available to isurv subscribers. Sign up for a free-trial to access this content.

Alternatively, you can gain access now and purchase isurv online here

.