Solland International Ltd v Daraydan Holdings Ltd

This information is only available to paying isurv subscribers.

[2002] EWHC 220 (TCC) 83ConLR109 Adjudication - construction contract - enforcement of adjudicator's decision - cross-claim - cross-claim for liquidated damages - notice of intention to withhold payment Solland were building contractors undertaking construction work on behalf of Daraydan. Disputes arose with regard to payment of...