Group element 6: Prefabricated buildings and building units

Group element 6 comprises the following elements:

6.1 Prefabricated buildings building and units
Note: Where on-site testing and commissioning is required to be measured under sub-elements 6.1.1 to 6.1.3, the terms shall include the following works:

1 Testing includes:
Testing equipment and consumables
Calibration
Site installation tests
Static testing, including testing records
Performance testing, including performance test records
Fuels required for testing
2 Commissioning, includes:
Commissioning, including preliminary checks, setting systems and installations to work and regulation thereof, and commissioning records
Temporary operation of equipment to employer’s requirements
Fuels required for commissioning
3 Setting all mechanical and electrical services and installations to work after completion of commissioning (initial operation)

Effective from 1 January 2013