Cases - Wormald Engineering Ltd v Resources Conservation International
Record details
- Name
- Wormald Engineering Ltd v Resources Conservation International
- Date
- [1992]
- Citation
- 8 BCL 158
- Keywords
- Contract - condition precedents - notices - variations - payment for delay and disruption - whether the contractor was entitled to payment for the variation where it had failed to comply with the condition precedent
- Summary
-
In an Australian case the contractor failed to give notice to the employer after a variation order, as required under the contract. The contractor was paid for some of the costs occasioned by the variation by the employer, but subsequently claimed for delay and disruption. It was held, for reasons similar to those in Jennings Construction v Birt, that the giving of notice was a condition precedent to any entitlement for additional payment.