Cases - Harbour & General Works Ltd v Environment Agency

Record details

Name
Harbour & General Works Ltd v Environment Agency
Date
[2000]
Citation
1 WLR 950
Legislation
Keywords
Arbitration - building contract - arbitration proceedings - extension of time limits for commencing arbitration - whether the court should exercise its discretion to extend the time limits for commencing an arbitration - s. 12 of the Arbitration Act 1996
Summary

The statutory time limits for commencing arbitration can only be extended where the circumstances are such as to be beyond the reasonable contemplation of the parties to the agreement.