Cases - Cellulose Acetate Silk Company Ltd v Widnes Foundry (1925) Ltd
Record details
- Name
- Cellulose Acetate Silk Company Ltd v Widnes Foundry (1925) Ltd
- Date
- [1933]
- Citation
- AC 20; HL
- Keywords
- Construction contract – measure of damages – delay – penalty sum per week agreed – liquidated damages – inadequacy of damages – whether limited to liquidated damages rather than actual loss suffered
- Summary
-
In this case, a contract for the construction of an acetone recovery plant provided that if the work was not completed within the specified time, the respondents were to pay a penalty of £20 per week. The works were completed weeks late, but the claimant's losses were far higher than the £600 liquidated damages. The House of Lords held that the claimant's recovery was limited to £600.