Post-tender estimates

Post-tender estimates

A post-tender estimate is the link between tender reporting and cost reporting. It is prepared after all construction tenders have been received and evaluated it is incorporated into the tender report and becomes the first cost report.

It is a pre-contract activity and, as such, it is more flexible in its approach. It does relate back to a milestone document (i.e. the tender return) but it is not limited to the works carried out under the contract.

As it is an estimate, it relates to the project and will cater for aspects of works that do not form part of the contract, for example, utility connections, professional fees and advanced enabling works.

When undertaking a post-tender estimate it is important to consider the form of contract that will be reflected in the tender return. Much of this comes down to risk allocation, refer to NEC3 contract types as scheduled below.

The ECC comes in 6 options which are:

Main option Contract type Pricing mechanism Risk allocation
A
Priced contract with activity schedule
Lump sum
Contractor
B
Priced contract with bills of quantities
Remeasurement
Client
C
Target contract with activity schedule
Cost reimbursement with pain-gain mechanism
Shared
D
Target contract with bills of quantities
Shared
E
Cost re-imbursement contract
Cost re-imbursement
Client
F
Management contract
Cost re-imbursement
Client

The tender will have included risk allocation as required by the contract. The post-tender estimate needs to consider what aspects of the project remain as client risk. Where risk is shared or wholly owned by the client then these should form part of the Quantitive Risk Assessment (QRA) which goes to inform the risk provision the client needs to maintain for the project.

This section is maintained by Patrick McNamara of AECOM.