Monitoring progress

This document is only available with a paid isurv subscription.

Histograms and 'S' curves are particularly useful for progress monitoring purposes and for the identification of trends. Figure 17 is a simple 'S' curve that tracks the actual quantity of concrete poured against the anticipated planned quantity. It shows that the concrete poured up until around week 7 was slightly ahead of...