A short delay between making and issuing the decision may be acceptable. The statutory time limit applies to the making of the decision.
A clear reservation of position at the outset of the adjudication that contained a clear statement as to the nature and scope of the reservation was sufficient to enable Dalkia both to partake in the adjudication and to subsequently challenge the adjudicator’s decision on the basis of the reservation previously made.