Mowlem plc (trading as Mowlem Marine) v Stena Line Ports Ltd

This document is only available with a paid isurv subscription.

[2004] EWHC 2206 (TCC) Tendering and procurement Where work was done under a letter of intent limiting Mowlem's entitlement to payment to a maximum of £10 million, the court refused to imply a term that the contractor would also be paid a reasonable amount for work...